Run the Logic Sensitivity Check
Run the Logic Sensitivity check to identify how potential delays affect key activities or milestones later in the project.
To run the Logic Sensitivity check, complete the following steps:
- Select the S2 // Logic tab.
- In the Logic Analysis group, click Logic Sensitivity.
-
On the Logic Sensitivity screen, enter information into the following fields:
- The Nudge Activity will be the starting point of the test. Select any activity or milestone from your project. A simulation will be run where a delay is added to this activity to see if it impacts an activity or milestone later in the project.
- The Nudge Duration is the number of days by which you would like to nudge, or delay, the Nudge Activity. By default this number is set at 600 days.
- The Target Activity is the activity on which you would like to test the impact.
- Click Analyze.
Parent Topic: S2 // Logic Tab Procedures